Slipway Update

The Contractor (CIVCO) returned to site last week and following preparation works they then undertook two further concrete pours this week on Tuesday and Thursday; the new slip is now nearly complete to boat yard level. The final pours will be completed early next week and the contractor will then take approximately three weeks to complete the positioning of rock armour, removal of the coffer dam and general reinstatement works and should have the slip complete by the end of May.